Texas has shut down the web portal for its automated construction permit filing system and suspended construction permits for 17 data center projects. The action followed reports from 404 Media that a group of Texans found the state continued to issue permits despite Governor Greg Abbott calling for a pause in September.
On Monday, the watchdog groups FracTracker Alliance and Public Citizen published reports detailing more than two dozen permits issued to Texas data center projects. On Tuesday, the website for STEERS – an application filing system for construction projects run by the Texas Commission on Environmental Quality (TCEQ) – returned a 404 error.
By Wednesday, the site displayed this message: “TCEQ’s electronic filing application used for automatic authorizations has been temporarily shut down to ensure all applications are reviewed by agency staff to determine if they are related to data centers.”
Before TCEQ shut the portal down, 404 Media viewed 17 different permits related to data center projects and saw that they had been moved from “active” to “suspended” in the TCEQ central registry.
“STEERS is a portal that TCEQ uses to rubber stamp construction approvals,” Sam Law, a researcher at FracTracker Alliance, told 404 Media. “It seems like they forgot about it and the portal has been quietly issuing approvals since the governor’s order for a pause, including for OpenAI and Amazon this Monday and Tuesday.”
The 17 suspended permits relate to stormwater construction. This approval allows construction companies to raise and level ground. It is a key, and sometimes final, part of the approval process for any construction project in Texas.
“Now they’ve taken the unprecedented step of suspending 17 approvals and taking down the whole site as they switch to a more involved human review process,” Law said. “The irony is not lost on me. When fighting the AI data centers build out, it’s nice to have a clear example of how some work is better left to humans.”
Law said he reached out to TCEQ and did not hear anything from them. The commission also did not respond to 404 Media’s request for comment. “I am very concerned that since contractors are accustomed to this automated approval process, they might not be aware of the suspension and continuing construction at some of the largest hyperscale facilities in Texas,” Law said.
What it means
The shutdown forces a manual review process for permits. This change means human staff must now check applications against the governor’s pause order. Contractors who relied on the automated system must now wait for individual decisions. The state admits the previous system failed to filter out projects that should have been stopped.